We provide real PK0-003 exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass CompTIA PK0-003 Exam quickly & easily. The PK0-003 PDF type is available for reading and printing. You can print more and practice many times. With the help of our CompTIA PK0-003 dumps pdf and vce product and material, you can easily pass the PK0-003 exam.

Q141. - (Topic 1) 

A project team has to implement a key part of their solution from an external vendor. After sending out an RFP, the team has narrowed the possible providers down to three. Which of the following should the project manager do NEXT? 

A. Hold a steering committee meeting to discuss the options 

B. Ask the project team to take a vote on the vendor 

C. Begin contract negotiations with the lowest offer 

D. Contact project stakeholders individually and discuss the RFP 

Answer:


Q142. - (Topic 2) 

Given the following activity: 

Provide details of errors within the software that occur during verification testing that provide enough evidence that allows the software developers to resolve the errors. 

Which of the following components is this known as within the quality management plan? 

A. Quality control 

B. Quality metrics 

C. Quality baseline 

D. Quality assurance 

Answer:


Q143. - (Topic 2) 

A project manager has projected an overwhelming response to a product launch. Which of the following BEST describes this event? 

A. A constraint 

B. A risk 

C. A performance index 

D. An issue 

Answer:


Q144. - (Topic 1) 

It is the first week after a project kick-off. The project team is not making much progress on decisions needed and are disagreeing with each other. Which of the following represents the team's current stage? 

A. Storming 

B. Norming 

C. Forming 

D. Performing 

Answer:


Q145. - (Topic 1) 

After identifying a change needed in the system, which of the following is the NEXT action the stakeholder should perform? 

A. Inform the developer 

B. Inform the resource manager 

C. Inform the project manager 

D. Inform the project sponsor 

Answer:


Q146. - (Topic 3) 

A two year project is three months away from launch when a new change is introduced. Once the project manager performs an impact analysis, which of the following should be done NEXT? 

A. Determine new milestones 

B. Update the project plan 

C. Meet with the stakeholders 

D. Level the resources 

Answer:


Q147. - (Topic 1) 

Which of the following is a characteristic of a product life cycle? 

A. Is constrained by time and resources 

B. Incorporates initiating through closing 

C. Has a plan for ongoing operations 

D. Develops a unique product 

Answer:


Q148. - (Topic 3) 

A project manager is leading a training session relating to the software development lifecycle in use at the organization. Several of the developers report that the CCB is unnecessary and that it simply delays development efforts on critical projects. Which of the following would be the BEST explanation for the purpose of the CCB? 

A. The CCB ensures that changes have been approved by the end user prior to analysis. 

B. The CCB ensures that stakeholders are aware of the impact of the change on the project budget. 

C. The CCB ensures that properly analyzed and approved items are submitted for implementation. 

D. The CCB ensures that implementations are documented and budgeted by the development team. 

Answer:


Q149. - (Topic 1) 

Which of the following project plan components would include information regarding the management of issues? 

A. Project Management Plan 

B. Human Resources Plan 

C. Test Mangement Plan 

D. Scope Management Plan 

Answer:


Q150. - (Topic 3) 

A project manager is leading a discovery session involving a quality problem discovered in the manufacturing process for a time-sensitive product. In an effort to expedite the process of resolving quality control issues the team would like to focus on improvements that would result in the greatest positive impact to the quality of the product. A data set has been collected over time and is ready for use by the project team. Which of the following graphical data tools would be MOST appropriate to help the project team achieve its stated goals? 

A. Pareto chart 

B. Delphi model 

C. Run chart 

D. Histogram 

E. Ishikawa diagram 

Answer: